After the AI Data Centre Surge: What Liquid Cooling and Chilled-Water Systems Ask of Pumps
AI is turning data centres from one large electricity user among many into a standalone variable in grid planning. More electricity in means more heat out, and the thing that carries heat from the chip to the outdoors is a water loop driven by pumps. This article draws on public material from the International Energy Agency (IEA), Lawrence Berkeley National Laboratory (LBNL), ASHRAE and the Uptime Institute to lay out the real numbers on data centre power and cooling, and what liquid cooling and chilled-water systems now ask of pumps.
Power demand: growing much faster than other sectors
According to the IEA report Energy and AI (April 2025), global data centres used about 415 TWh in 2024, roughly 1.5% of world electricity. In its Base Case consumption reaches about 945 TWh in 2030, close to 3%, and about 1,200 TWh in 2035. From 2024 to 2030 it grows at around 15% a year, more than four times faster than electricity use in all other sectors combined. Installed data centre capacity is projected to rise from about 100 GW today to about 225 GW in 2030, and the United States and China together account for nearly 80% of global growth to 2030.
Power density is rising too. The IEA notes that a single compute node with eight accelerators can be rated above 10 kW, while a two-accelerator node is rated below 2 kW. Racks are getting hotter and air cooling is struggling, which is the direct reason liquid cooling is moving into the mainstream.
For the United States, the LBNL 2024 United States Data Center Energy Usage Report (December 2024) estimates that data centres used 176 TWh in 2023, or 4.4% of national electricity, and projects 325 to 580 TWh in 2028, or 6.7% to 12.0%. The report stresses that the sector lacks transparent data and that the range is wide; the choice of cooling system, such as a shift to liquid cooling or away from evaporative cooling, is itself one of its scenario variables.
How much goes to cooling: PUE in numbers
Power usage effectiveness (PUE) is total facility electricity divided by IT equipment electricity. A PUE of 2 means 1 kWh of overhead, mostly cooling, for every 1 kWh used by IT. The IEA puts enterprise data centres at around 2 and large hyperscale sites just under 1.15, and says cooling's share of total consumption runs from about 7% in efficient hyperscale facilities to more than 30% in inefficient enterprise ones.
| Indicator | Figure | Source |
|---|---|---|
| Global weighted-average PUE | About 1.41 in 2024; about 1.29 in 2030 (Base Case) | IEA (2025) |
| US average PUE | About 1.6 in 2014, about 1.4 in 2023, projected 1.15 to 1.35 in 2028 | LBNL (2024) |
| Infrastructure share of US data centre electricity | About 40% in 2014, about 30% in 2023 | LBNL (2024) |
One point is easy to miss. A falling PUE means less cooling electricity per unit of IT electricity; it does not mean the cooling system is getting smaller. IT heat load is growing by double digits a year, so the water loops must move more heat in absolute terms, even if each unit of heat costs less to move and reject. We found no authoritative public statistic for the pump share of cooling electricity, so we give none.
Liquid cooling classes and what they mean for pumps
In the fifth edition of its Thermal Guidelines (2021), ASHRAE TC 9.9 classifies liquid cooling by facility supply-water temperature into W17, W27, W32, W40, W45 and W+, where the number is the upper supply temperature in degrees Celsius; every class has a lower limit of 2 °C. W17 and W27 are typically served by chillers and cooling towers, with an optional water-side economiser. W32 and W40 typically run without chillers in most locations. W45 and W+ typically run without chillers, although some locations are not suited to dry coolers.
The LBNL report adds that liquid-cooled IT can often run at higher water temperatures than air-cooled IT, so water-side economisers can meet demand for much of the year. Warmer supply water saves energy but leaves the chip less temperature margin. An ASHRAE white paper gives a case: in its dense cold-plate configuration, W27 can support about 500 W per CPU, while W45 cuts cooling capability to roughly that of an air-cooled system with a low cold-aisle temperature; one remedy is a more capable pump and heat exchanger in the coolant distribution unit (CDU). The practical reading is that high-temperature designs demand more flow, head and heat-exchange area, so sizing cannot rest on a rule-of-thumb temperature rise.
Note that the white paper's "750 kW CDU serving eight racks" is a modelling assumption, not a market standard. We also found no international product standard written specifically for data centre cooling pumps, so selection should follow the project specification and the IT equipment maker's flow, pressure and water-quality requirements.
Reliability: redundancy is the default
The Uptime Institute Tier system is the common language for data centre reliability. In its public description, Tier II calls for redundant capacity components in power and cooling, and its list explicitly includes pumps; Tier III requires concurrent maintainability, so any equipment can be taken out for service without affecting IT; Tier IV adds fault tolerance and requires continuous cooling. The IEA likewise notes that UPS batteries and backup generators exist to meet the extremely high reliability data centres must deliver. For pumps this translates into N+1 (one spare) or even 2N pump sets, automatic changeover, in-service replacement, and life validation for continuous duty.
The ASHRAE white paper also lists operating points that bear directly on pumps: build and maintain a wetted-materials list during design so every material touching the coolant is approved; use clean construction practice and plan for flushing; put drip pans with leak detection under overhead piping; and keep supply-water fluctuation within the temperature and flow envelopes (magnitude, duration and rate of change) that IT equipment makers specify.
Water is a boundary condition too
The IEA estimates that a 100 MW hyperscale data centre in the United States uses about 2 million litres of water a day on average, over 60% of it indirect (power generation and so on), and that global data centre water consumption is about 560 billion litres a year today, possibly reaching about 1,200 billion litres in 2030 in the Base Case. It also notes that direct-expansion cooling uses far less water than airside economiser and adiabatic cooling with water-cooled chillers, the latter used in about half of hyperscale facilities. Water limits push projects toward dry coolers and closed loops, which changes pump duty points and water-quality requirements.
What this means for pump makers
- Product positioning: the typical duty is a closed loop with small to medium flow, moderate head and continuous running, split between large primary-side chilled and condenser water pumps and small secondary-side pumps inside CDUs. Sort your range into those two groups and use curve search to check for gaps in coverage.
- Variable speed and control: compute load swings quickly, and supply temperature and flow must stay inside the IT maker's envelope. For multi-pump variable-speed operation, first check low-load and pump-switching duty points with operating-point simulation, then verify speed range and minimum flow against our article on variable-frequency pump control.
- Redundancy and pump sets: an N+1 set needs matched parallel curves and enough remaining capacity when one pump fails; check this in pump units.
- Materials and fluid compatibility: prepare a wetted-materials list, seal and elastomer compatibility data, and cleanliness documentation (factory flushing, contamination-proof packing). Glycol blends and limits should follow customer and IT-maker requirements.
- Noise and vibration: machine rooms often sit next to occupied space, so publish sound power and vibration data.
- Validation and testing: beyond factory performance tests, keep records of continuous running, start-stop cycling, leakage and changeover; these persuade data centre owners more than a point or two of efficiency.
- Motors and efficiency: with continuous duty, electricity dominates cost. Use motor selection and analysis to compare running costs across IE classes; the regulatory background is in our review of pump and motor efficiency standards.
- Market judgement: growth is concentrated in the United States and China. Confirm certification, materials and test requirements of target projects before exporting, and plan capacity on scenarios rather than a single forecast, since both the IEA and LBNL stress the uncertainty.
References
- International Energy Agency (IEA), Energy and AI, April 2025, iea.org
- Lawrence Berkeley National Laboratory (LBNL), 2024 United States Data Center Energy Usage Report, December 2024, eta-publications.lbl.gov
- ASHRAE TC 9.9, 2021 Equipment Thermal Guidelines for Data Processing Environments (5th edition) reference card, ashrae.org
- ASHRAE TC 9.9 white paper, Emergence and Expansion of Liquid Cooling in Mainstream Data Centers, 2021, ashrae.org
- Uptime Institute, Tier Classification System, uptimeinstitute.com